MYRA

Potong Pasir, Singapore
SITE PROGRESS
Site Photos

End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.

End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.

End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.

End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.

End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.

End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.

End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.

End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.

End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.

End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.

End November 2022
Level 1 slab 80% completed, Level 2 slab 50% completed.

End November 2022
Level 1 slab 80% completed, Level 2 slab 50% completed.

End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.

End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.

End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.

End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.

End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.

Lorem ipsum

End June 2022
The basement excavation is in progress and is about 80% completed.

Lorem ipsum

End June 2022
The basement excavation is in progress and is about 80% completed.

Lorem ipsum

End May 2022
The basement excavation is in progress and is about 50% completed.

Lorem ipsum

End May 2022
The basement excavation is in progress and is about 50% completed.

Lorem ipsum

End April 2022
The basement excavation is in progress and is about 35% completed.

Lorem ipsum

End April 2022
The basement excavation is in progress and is about 35% completed.

Lorem ipsum

End March 2022
The basement excavation is in progress and is about 30% completed.

Lorem ipsum

End March 2022
The basement excavation is in progress and is about 30% completed.

Lorem ipsum

End February 2022
The piling is completed, and the excavation to basement had commenced.

Lorem ipsum

End February 2022
The piling work is completed and excavation to basement had commenced.

Lorem ipsum

End January 2022
The contractor is doing piling works, about 90% completed.

Lorem ipsum

End January 2022
The contractor is doing piling work, about 90% completed.

Lorem ipsum

End December 2021
The contractor is doing piling works, about 90% completed.

Lorem ipsum

End December 2021
The contractor is doing piling work, about 90% completed.

Lorem ipsum

End November 2021
The contractor is doing piling works, about 65% completed.

Lorem ipsum

End November 2021
The contractor is doing piling work, about 65% completed.

Lorem ipsum

End October 2021
The contractor is doing piling, about 40% completed.

Lorem ipsum

End October 2021
The contractor is doing piling, about 40% completed.

Lorem ipsum

End September 2021
Ground works in progress and the contractor is doing soil improvement piles.

Lorem ipsum

End September 2021
Ground works in progress and the contractor is doing soil improvement piles.

Lorem ipsum

End August 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End August 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End June 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End June 2021
Ground works in progress and the contractor is doing site setup.

Lorem ipsum

End December 2020
Ground works in progress.