MYRA
2022
End Apr 2022The basement excavation is in progress and is about 35% completed.
End April 2022The basement excavation is in progress and is about 35% completed.
End March 2022The basement excavation is in progress and is about 30% completed.
End February 2022The piling is completed, and the excavation to basement had commenced.
End February 2022The piling work is completed and excavation to basement had commenced.
End January 2022The contractor is doing piling works, about 90% completed.
End January 2022The contractor is doing piling work, about 90% completed.
2021
End December 2021The contractor is doing piling works, about 90% completed.
End December 2021The contractor is doing piling work, about 90% completed.
End November 2021The contractor is doing piling works, about 65% completed.
End November 2021The contractor is doing piling work, about 65% completed.
End October 2021The contractor is doing piling, about 40% completed.
End September 2021Ground works in progress and the contractor is doing soil improvement piles.
End August 2021Ground works in progress and the contractor is doing site setup.
End June 2021Ground works in progress and the contractor is doing site setup.
2020
End December 2020Ground works in progress.