End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.
End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.
End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.
End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.
End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.
End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.
End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.
End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.
End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.
End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.
End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.
End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.
End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.
End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.