End November 2023
The architectural, M&E and landscape works are all in progress. External boundary wall in progress. Target to obtain TOP in 1H 2024.
End November 2023
The architectural, M&E and landscape works are all in progress. External boundary wall in progress. Target to obtain TOP in 1H 2024.
End October 2023
The architectural, M&E and landscape works are all in progress. Target to obtain TOP in 1H 2024.
End October 2023
The architectural, M&E and landscape works are all in progress. Target to obtain TOP in 1H 2024.
End September 2023
The tower crane has been removed, and the architectural and M&E works are in progress at lower levels. Target to obtain TOP in 1H 2024.
End September 2023
The tower crane has been removed, and the architectural and M&E works are in progress at lower levels. Target to obtain TOP in 1H 2024.
End August 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.
End August 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.
End July 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.
End July 2023
The structural roof slab is completed, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.
End June 2023
The structural slab is in progress at roof level, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.
End June 2023
The structural slab is in progress at roof level, and the architectural and M&E works are at lower levels. Target to obtain TOP in 1H 2024.
End May 2023
The structural slab is in progress at level 11, and the architectural and M&E works are at level 2- level 5. Target to obtain TOP in 1H 2024.
End May 2023
The structural slab is in progress at level 11, and the architectural and M&E works are at level 2- level 5. Target to obtain TOP in 1H 2024.
End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.
End April 2023
Level 10 structural slab is in progress. Lower floors architectural and M&E are in progress.
End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.
End March 2023
The basement construction works is completed. Level 8 structural slab is in progress.
End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.
End February 2023
The basement construction works is about 97% completed. Level 6 structural slab is in progress.
End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.
End January 2023
The basement construction works is about 95% completed. Level 4 structural slab is in progress.
End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.
End December 2022
The basement excavation about 95% completed. Level 2 structural slab completed. Level 3 structural slab in progress.
End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End October 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End September 2022
The basement excavation about 95% completed. Level 1 structural slab 50% completed.
End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.
End August 2022
The basement excavation is in progress and is about 90% completed. Slab in progress to level 1.
End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.
End July 2022
The basement excavation is in progress and is about 85% completed. Slab in progress to level 1.